|
MacDonald talks on Navajo energy development
By Kathy Helms
Diné Bureau
WINDOW ROCK Long before Desert Rock Energy Project
was ever thought of, the Navajo Nation had its own plans to build a power
plant. But that was scuttled in 1982 after Chairman Peter MacDonald lost
his bid for re-election.
"One of the things that we had going back in the late 1970s was to
build a 250-megawatt power plant over by Standing Rock (N.M.)," he
said Tuesday following a Monday evening presentation on the history of
Navajo Nation water rights in Dilkon.
Standing Rock
"Standing Rock is between Coyote Canyon and Crownpoint.
It's a small chapter there, but they have huge reserves of coal right
in that area. The coal seams run about 30 feet deep. That's how thick
it is. We had a great deal of geology work done there for coal seams and
also for water. Then we hired a power engineering firm out of Kansas City
to design a 250 megawatt plant," MacDonald said.
"We went to the chapter and after a lot of negotiation with the chapter
they approved it, and then we started doing design work. This would be
a 100 percent Navajo power plant. Nobody else involved. The first customer
would be Navajo."
At that time, he said, the Navajo Nation was using somewhere around 50
megawatts of power. Navajo Tribal Utility Authority, "if I remember
right, is using about 80 megawatts of power. So this 250-megawatt was
designed to be sufficient for a number of years, and the excess coming
from that plant would be sold to whoever wants extra energy."
"We had the engineers design it and we were just about ready to launch
it. At that time the big question was who was going to run it, NTUA or
somebody else.
"On the generation side we wanted to set up a separate entity of
NTUA to be responsible for generation. The other part, the distribution
part, they have always been doing that. They buy the power and then distribute
it," MacDonald said.
NTUA
In this case, NTUA would get its power from the generating plant that
was going to come on line in Standing Rock.
"We were lining up the coal mining part as well. Part of the effort
of Navajo Engineering Construction Authority was to do major engineering
projects as well, but that's another story," MacDonald said.
"When I left in 1982, this thing was right at the point of putting
the final touches on it to go to the tribal council for approval. All
of the ecological clearances and environmental impact and all those were
done."
Mickey Dalton was NTUA general manager at the time and was very much involved
with the Standing Rock project, MacDonald said. "Of course, I left
in 1982 and when I came back that project was scuttled and in its place
they had set up this DPA.
"They scrapped the Standing Rock thing and they were going to joint
venture with the state of New Mexico along with some other major companies
like Bechtel and Southern California Edison Co., New Mexico Public Service
Co., GE, and I forget who else. They had a consortium and they were pitching
in their monies to support DPA, Din Power Authority," he said.
When he came back into office in 1987, MacDonald stopped it.
"I had a meeting with the major principles in Denver and I said,
'No way are you going to do that, because you are just taking advantage
of the Navajo.' They wanted Navajos to kick in the right-of-way for a
500 KV line and things like that. I said, 'No. The right-of-way is separate.
We don't even want to talk about that.' "
Coal use
The coal they were going to use was on land the Navajo acquired in Eastern
Navajo Agency by Chaco Canyon, according to MacDonald.
"We picked that land back in the 1970s because it also had a lot
of coal. There's a huge coal reserve underneath it. We picked that land
when we were in the process of dealing with Congress on the Navajo-Hopi
land dispute.
"When they decided for us to give some land to the Hopis, we said
that we've got to get some land in return. So that's one of the lands
that we picked over there. What New Mexico discovered was that that land
had a lot of coal in it, so then I guess they came to the tribe when I
was out and said, 'Let's make a deal.'
"So they scuttled the Standing Rock project," MacDonald said.
"Everything just went downhill after that. When I came back, it was
gone and DPA was there. I stopped it, but of course, I was only in two
years after that."
MacDonald said there also are many natural gas deposits under Navajo Indian
Irrigation Project, which is rapidly being leased out in chunks to oil
and gas companies now doing business on the Navajo Nation, and for which
the Nation is receiving little royalty.
"A fault line runs diagonally across into Colorado, all the way up
to Wyoming. Along that fault line, there's all these oil and gas deposits.
That's why the San Juan area has been a good oil producer for many years,
and there's still a lot of oil in there.
"On the NAPI property, on the southern end, the fault line runs underneath
there. We made some preliminary drilling in those areas and there is natural
gas in there.
"At one point we were talking about having a cogeneration plant there.
It was a smaller one, like 30 megawatts. Of course, you could increase
it as much as you want. But those were possibilities."
Because it was on Navajo Agricultural Products Industry property, it was
decided that NAPI should benefit from it.
"The idea was, trying to become self-sufficient instead of just sitting
and waiting for the federal government to give you money," MacDonald
said.
|
Friday
May 5, 2006
Selected Stories:
Officials tight lipped on
talks with developer
Diné chapter houses log on to new
technology
Acoma museum set to open on May 27
MacDonald reviews history of Navajo water
Deaths
|